Alterative dispute resolution Belfast Dublin London
  Home QG Guides Legislation Case Law Policy Documents Our Services Training Links Contact Us  
 
 

Remedies

Q1. When will the court grant and injunction.

A1. Due to the difficulties in assessing damages, which will be explored below, it is considered that injunctive relief should be considered as the primary remedy, Partenaire Limited v Department of Finance and Personnel [2007] NIQB 100 at 13.

When an aggrieved contractor receives notice from the contracting authority that it intends to award the contract to another, and where the contractor believes that there has been a breach of the contracting authority’s duty then it may apply for an interim injunction to restrain the contracting authority from awarding the contract.

The court, when faced with such an application will apply the American Cyanamid test (American Cyanamid Co v Ethicon Co Limited [1975] AC 396). The criteria laid out in that case are:

  • is there a serious issue to be tried?
  • are damages an adequate remedy?
  • does an undertaking in damages provide adequate protection?
  • where does the balance of convenience lie?

It is, of course, correct that in applying these criteria each case will turn on its own of facts. In Pantenaire the Court, in considering whether or not damages would be an adequate remedy, took into account that the exercise to measure the damages would be difficult, but not impossible. Nevertheless, the Court was not persuaded that damages would be an adequate remedy in that particular case. In that case the Court then went on to consider the adequacy of the qualified undertaking in damages being offered by the applicant. The Court took into account that the potential loss could be overwhelming and that if it imposed a “full” undertaking, it would effectively prohibit a private sector contractor seeking interlocutory injunction, and accepted the qualified undertaking offered.

In McLaughlin & Harvey Limited v Department of Finance and Personnel [2008] NIQB 25 the Court was not persuaded that the award of damages would be inadequate. The Court then considered the fact that the cross undertaking in damages might not fully compensate the defendant, and although not an insurmountable barrier, was a factor in the balance against the application. No injunction was granted.

Q2. Overview of available remedies

A2. The primary remedies available for either breach of the tendering contract, or for breach of the PCR ‘06 is application for an injunction and/or a claim for damages.

Should a challenge be made by way of application for judicial review, the remedies would include a mandatory order, a prohibition order, a quashing order or a declaration. Although very rare, a claim could also be made founded on the Tort of Misfeasance in Public Office.

Reg.47 of PWC ‘06 provides that:

“…without prejudice to any other powers of the Court, in proceedings brought under this regulation the Court may –

(a) by interim order suspend the procedure leading to the award of the contract…or suspend the implementation of any decision or action taken by the contracting authority…and

(b) if satisfied that a decision or action taken by a contracting authority was in breach of the duty owed …

i order the setting aside of that decision or action or order the contracting authority to amend any document; or

ii award damages to an economic operator which has suffered damage as a consequence of the breach; or

iii do both of those things.”

It should be noted that Reg.47(9) provides that the Court does not have power to order any remedy other than an award of damages for breach of a duty where the contract, in relation to which the breach has occurred, has been entered into.


book a free consulting
 

Quigg Golden Company
Brochure

Contract Advice & Preparation

Download


 

 
print page